Here’s the latest news in the long, drawn-out dispute over proposed faculty housing at the Rev War battlefield. Unfortunately, it’s not the good kind of news, but the Princeton Battlefield Society is going to keep fighting the good fight.
Judge Jacobson’s decision upheld the approval that Princeton’s Planning Board gave the Institute last year for an amended version of the project, which had first been approved in 2012. The IAS wants to build 15 units, clustering eight townhouses and seven single-family dwellings on a seven-acre parcel. The Battlefield Society says the houses would be on land where American and British soldiers fought during the Revolutionary War in 1777.
The Delaware & Raritan Canal Commission blocked the project in 2012 because of its encroachment on a stream corridor, and the IAS tweaked the plans to slightly shrink the footprint. It was that amended application that the Planning Board approved last year. The Battlefield Society said that because of the amendments, the project is essentially new and the IAS should have to start over. The Planning Board did not agree, and Judge Jacobson concurred.
As part of the ruling, Judge Jacobson issued a temporary delay on any start of construction to allow time for the Battlefield Society to appeal.
“We respect Judge Jacobson’s opinion, but we do not believe she’s correct,” Mr. Afran said. “And we believe there are serious failings in what the Planning Board did three years ago and again [in 2010]. They refused to hear relevant evidence. This decision is an error and it ignores all of the duties of the Planning Board to protect historical sites.”
I wish the PBS good luck in the appeal process, and a tip of the hat for their effort to keep this battleground intact.